A. Spall repairs Koko Isle Bridge Hawaii Kai

(Click each picture to show enlarged image).

Click to enlarge
Spalls chipped out. Concrete and rebar cleaned by power wire brushing. Exposed rebar treated with "Extend" rust neutralizing coating.
Click to enlarge
Click to enlarge
Voids coated with epoxy bonding agent and filled with Thorite Rapid Vertical patching cement. After cure surfaces were finish coated with "Profinish" cement wash.
Click to enlarge


B. FMC East Oahu Dialysis Clinic Kapahulu, Oahu

(Click each picture to show enlarged image).

Click to enlarge
Floor cracks repaired by gravity epoxy injection. Floor then shot blasted to clean.
Click to enlarge
Primer and base coat of epoxy resin and terrazzo chip broadcast.
Click to enlarge
Clear finish resin applied to create a finished, seamless epoxy terrazzo floor. Looks just like a granite slab.


C. King St. Union 76 Service Station.

(Click each picture to show enlarged image).

Click to enlarge
Floor scarified and shot blasted. Cracks repaired using epoxy gravity injection. Leveling of floor by epoxy paste.
Click to enlarge
Finished floor, seamless Sikagard 62 epoxy coating with non-slip aggregate added.


D. Replaster and recoat of Dillingham Fountain, Waikiki.

(Click each picture to show enlarged image).

Click to enlarge
Entire fountain water blasted with 20,000 psi super high pressure to remove existing scaling cement and old coatings. We then replastered the entire fountain with Thoroseal waterproofing cement.
Click to enlarge
Pool was then coated with many coats of Ramuc underwater epoxy coating.


E. Strucutral cracking to Waikiki High Rise buttress.

(Click each picture to show enlarged image).

Click to enlarge
Cracks were cleaned by water blasting and compressed air dried. Propoxy 300 epoxy surface sealer goes over the cracks with plastic ports drilled in at intervals. Cracks injected with Propoxy 100 injection resin until filled.
Click to enlarge
Buttresses pick up severe tower loads requiring a high strength repair like epoxy injection to provide a full depth weld.


F. Ceiling crack repairs to the Ihilani Hotel, Oahu

(Click each picture to show enlarged image).

Click to enlarge
Major scaffolding work required over ponds.
Click to enlarge
Thousands of lineal feet of epoxy crack repairs required to repair plaster ceilings.
Click to enlarge
Painters and crack repair men on scaffolding above shark ponds.


G. Large scale edge spalling at Pali Palms Building.

(Click each picture to show enlarged image).

Click to enlarge
Sandstone concrete is very porous allowing extensive moisture penetration into the structure causing large scale rebar rusting and resulting spalling.
Click to enlarge
Click to enlarge
After chipping out and surface treatment, spalls are filled with Thorite Rapid Vertical high strength patching cement.
Click to enlarge
Click to enlarge
High work requires hanging platform scaffolding.
Click to enlarge
Click to enlarge
Because the sandstone cement is so porous repairs are coated with a matching acrylic coating to keep future moisture out.


H. Marco Polo apartments water bridge.

(Click each picture to show enlarged image).

Click to enlarge
Bridge structure was meant to provide a decorative pond sculpture where high tide waters would flow through concrete channels. However, the channels had too much rebar close to the concrete surface.
Click to enlarge
Loose concrete is chipped out and surfaces cleaned. Channels are formed and filled with concrete.
Click to enlarge
  
Click to enlarge
Repairs are then coated with epoxy under water coating.
Click to enlarge
  


I. Tank salvage, rum and ethanol plant, Kapolei.

(Click each picture to show enlarged image).

Click to enlarge
Salvaged steel plantation tanks dug out of the ground. Tanks were tar coated to protect from rust.
Click to enlarge
Tanks were sandblasted inside and out. Epoxy primer is installed just after blasting.
Click to enlarge
Tanks finish blasted ready to be used for water storage.
Click to enlarge
Inside plant, fermenting tanks coated with epoxy and urethane coatings.


J. Kalakaua Bridge major restoration, Waikiki

(Click each picture to show enlarged image).

Click to enlarge
Hundreds of square feet of spalls on total face of building. Hundreds of ceiling cracks were filled with epoxy and clear coated. Work accessed by hanging scaffolding. Spalls filled with Thorite Rapid Vertical cement.
Click to enlarge
Water blasting and some epoxy crack repairs.
Click to enlarge
Entire bridge coated with Thorowall. Surface still looks good after two decades.


K. Tunnel wall leaks, Schofield Barracks fresh water pump station.

(Click each picture to show enlarged image).

Click to enlarge
Access to pump chambers is over one quarter mile under ground. Chambers accessed by miners car on train tracks. Pumps are just above Oahu’s Aquifer. Leaks are under severe pressure due to weight of water pushing against chamber walls many hundreds of feet below ground. This kind of epoxy injection requires high pressure pumps.
Click to enlarge
Hundreds of feet of injection performed in chambers. Surfaces painted as repairs progress.


L. Patisserie Bakery, King Street Honolulu fire damage repairs

(Click each picture to show enlarged image).

Click to enlarge
Floors severely charred from fire requiring shot blast clean.
Click to enlarge
Floors partially coated, this floor with water based low fume epoxy coating.